As early as 2006, PTss demonstrated through live field application that moisture mitigation in power transformers can be achieved online, without shutdown, while delivering measurable improvements in insulation health.

A 33/11 kV, 10/12.5 MVA power transformer at 33/11 kV Substation, Sector-17, Chandigarh underwent Online Transformer Dry-Out, with results that remain directly relevant to today’s asset management priorities.

Why this matters:

Moisture is a silent accelerator of transformer ageing. This case study validated nearly two decades ago that online dry-out is not merely maintenance, but a strategic reliability lever supporting life extension, deferred capital expenditure, and improved network availability.

CXO Strategic Takeaway:

Investing in condition-based, online life-extension technologies delivers reliability dividends far exceeding their cost without disrupting operations.  

Encouraging outcomes achieved within 10 days:

Oil moisture: 35–40 ppm → <10 ppm (Main Tank & OLTC)
Cellulose insulation moisture: >4% (very wet) → 2.0%
Top-oil Relative Saturation (%RS): ~40% (critical) → <5%, evidencing restoration of insulation equilibrium
Polarization Index (PI): Consistent improvement across HV–E, LV–E, and HV–LV, indicating effective moisture removal
BDV: Improvement observed